Energy · needed from Abundance on Earth (2071)
A grid that spans the planet
The Sun never sets on the whole Earth. A grid that ties the continents together carries noon in one place to evening in another, and summer in one hemisphere to winter in the other, so it needs far less storage. High-voltage direct current already carries 12 gigawatts more than 3,000 km across China. The climb needs lines like it under the oceans.
The target
Lines between every continent that carry about a tenth of 100 TW, 10 TW, across time zones and seasons, so that sunlight anywhere on the day side serves demand on the night side, losing under 3 percent per 1,000 km.
What exists to build on
- The Changji to Guquan line in China, finished in 2018, carries 12,000 MW at 1,100 kV direct current over more than 3,000 km, a world record for voltage, power and distance. hitachienergy.com, 2019
- Statnett and National Grid's North Sea Link between Norway and Britain, 720 km long, began trial operation in 2021 as the world's longest subsea interconnector. statnett.no, 2021
- Xlinks planned 3.6 GW from solar and wind in Morocco to Devon over about 4,000 km of subsea cable; in June 2025 the UK government declined to back it with a contract. xlinks.co, 2025
- Sun Cable's Australia-Asia PowerLink plans up to 10 GW of solar and a 4,300 km cable to Singapore, which gave conditional approval to import 1.75 GW from 2035; in 2026 it was still seeking finance. abc.net.au, 2026
- The Great Sea Interconnector, a direct-current cable from Crete to Cyprus, will not be complete before the end of 2031, its Greek operator ADMIE said in November 2026, with 60 percent of the seabed surveys done. cyprus-mail.com, 2026
- State Grid of China proposed a Global Energy Interconnection in 2015, with transcontinental ultra-high-voltage lines linking Arctic wind and equatorial solar by 2050. powermag.com, 2016
What is missing
The longest line, Changji to Guquan, runs about 3,000 km within one country, and the longest subsea link, North Sea Link, is 720 km. Carrying daylight across time zones needs lines of 4,000 km and more, across oceans thousands of metres deep where a repair ship takes weeks to arrive. Each line needs several governments to agree, and the first long links have stalled on finance and politics: Xlinks lost British support in 2025, Sun Cable is still seeking finance, and the Great Sea Interconnector has slipped to 2031.